|
LISE
Updates
Laboratory for Integrated Science and Engineering (LISE)
Construction Updates
September 8th – September 14th, 2007
Friday, Sept. 7, and, possibly, into Monday, Sept. 10, concrete placements will
take place in the former Marcus Lab and the future lobby space on the west side
of the temporary barrier (i.e., out of sight). The concrete pump will be
positioned outside McKay and concrete will be pumped through a window into each
of these spaces; concrete trucks will enter/exit the courtyard space
throughout. The pump will generate noise and, I just imagine, that the concrete
being pumped into a building will look strange. The operation will begin as
early as 6:30 AM and may continue late into the afternoon(s).
For information on the Oxford St. Utility work
please click on the following:
Oxford
St. Utility Work Project
If
you have any questions or concerns please contact the
Mitigation Hotline at 617-496-0857 |