|
Northwest
Building
Project
Updates
Northwest Labs
Construction Update
August 2nd
- August 8th, 2008
Saturday 8/2/08
· On
Saturday a small crew will be completing landscaping activities.
·
Work will begin at 9am per City of Cambridge Construction
Ordinance.
Construction
Site:
·
Paving
operations at the entrance on the garage will take place on Monday (8/4/08) and
Tuesday (8/5/08). This work will affect the vehicular traffic to the garage and
the loading dock to 40 & 60 Oxford St. Police details will be present to direct
traffic and ensure safety.
·
On Monday, August 4th, 2008 all pedestrian pathways
to the garage will be open.
·
Sod
will be installed on the south side of Conant Hall this week. The fence will be
removed once this work has been completed.
If you
have any questions or concerns please contact the
Mitigation Hotline at 617-496-0857
|